The worked example on this page is the office risk assessment. This example covers a small company office of fourteen staff on the first floor of a shared building.
Step 1: identify the hazards
A hazard is anything that could cause harm: a wet floor, a ladder, a chemical, a heavy box, a trailing cable, a workload that cannot be done in the hours. Look for the things that could cause real harm, not every trivial risk. HSE suggests looking at:
- how people work, and how plant and equipment are used;
- what chemicals and substances are used;
- what safe or unsafe work practices exist;
- the general state of the premises.
Walk around and watch the work as it is actually done. Ask the people who do it: they know where the problems are. Check accident and ill health records, manufacturers' instructions and safety data sheets. Think about work that is not done every day, such as maintenance, cleaning and deliveries, and about harm that builds up slowly, such as back pain, dermatitis, noise and stress.
In the office example
6 hazards: slips, trips and falls on the same level, display screen equipment and desk work, electrical equipment and installations, fire, manual handling of loads, work related stress. Nothing exotic. That is normal for an office, and the assessment is short because of it.
Step 2: decide who might be harmed and how
For each hazard, write down the groups of people at risk, not their names, and how they could be hurt. Staff who do the work come first, but think about everyone else too: people working nearby, cleaners, contractors, visitors, delivery drivers and members of the public.
Some people need particular thought: new and young workers, new and expectant mothers, lone workers, people with a disability, and anyone who does not share a first language with the rest of the team. Where one of them is at greater risk, say so in the assessment and say what is done about it.
In the office example
- Slips, trips and falls on the same level: All staff and visitors. The kitchen floor and the entrance in wet weather are the problem areas.
- Display screen equipment and desk work: All fourteen staff use a screen for most of the day, including the two home workers.
- Fire: Everyone on the floor. One member of staff uses a wheelchair and has a personal evacuation plan.
Step 3: evaluate the risks and decide on precautions
For each hazard, decide how likely harm is and how serious it could be, look at what you already do, and decide whether more is needed. HSE's current guidance splits this into two parts, assessing the risk and controlling it, but the work is the same.
You are not expected to remove every risk. You are expected to do everything reasonably practicable, which means weighing the level of risk against the cost, time and effort of controlling it. Work down the order HSE gives:
- remove the hazard altogether if you can;
- redesign the job, or replace the material, machine or process with a safer one;
- organise the work to reduce how much people are exposed;
- put practical measures in place so the work is done safely;
- provide personal protective equipment, and make sure it is worn.
In the office example: slips, trips and falls on the same level
Rated 3 for likelihood and 3 for severity before the controls (9, medium), and 2 × 3 after (6, low). The controls in place:
- Spills are cleaned up straight away and the wet area is signed or cordoned until it is dry
- Walkways are kept clear of boxes, stock and equipment, and cables are routed away from walkways or covered
- Lighting is good enough to see the floor, including on stairs and outside at night
- Damaged flooring, loose mats and worn steps are reported and repaired
- Stairs have a handrail, the edge of each step is visible, and nothing is stored on them
- Entrance matting stops rain being walked in, and outside paths are gritted in icy weather
Rating the risk: the 5x5 risk matrix
A 5x5 risk matrix scores likelihood from 1 to 5 and severity from 1 to 5, and multiplies them. The score is out of 25. Rate each hazard twice: before the controls, to show how serious it is, and after them, to show what is left. HSE does not require a matrix, but it makes ratings consistent from one assessor to the next and shows on paper that the controls made a difference.